July 11 2023
Neighbourhood Meeting at Beasley Community Centre 4pm to 6pm
July 17 2023
West Phase Project Kickoff
Highway 97 to Seymour Road.
August 08 → September 20 2023
Winfield Creek Crossing Replacement Phase
Work in the creek will take place during the fish window of August 7 to September 20th.
September 15 2023
Roadway Paving
September 20 2023
West Phase Project Completion
West Phase - Highway to Seymour Road project phase completion.
September 19 2023
East Phase Project Kick Off
East Phase of the project will be kicked off.
Bottom Wood Lake Road to Lodge Road.
September 29 2023
Drainage Work Complete
October 20 2023
Roadway Paving Complete
October 27 2023
Pathway Paving Complete
October 30 2023
East Phase Project Completion
Bottom Wood Lake Road to Lodge Road complete.